- Chapter VII:
Facilities Engineering
      
         
			  
        
        
			 Facilities engineering, as distinct from new construction, refers
            to the series of operations carried out after basic structures are
            complete. It involves the services necessary to keep any large
            physical plant functioning efficiently: maintenance and repair of
            buildings, surfaced areas and grounds, service to refrigeration and
            air conditioning, minor ancillary construction, fire prevention,
            removal of trash and sewage, rodent and insect control, water
            purification, custodial services, management of property, engineer
            planning, supply of maintenance materials, and maintenance of
            equipment used in the upkeep of a base.
        
        
           
        
        
          For these operations the Army relied heavily on civilian
            contractors working under an arrangement in which the contractor
            provided labor, organization, and management, while the Army
            provided tools, repair parts, supply, mess facilities, and quarters
            for the work force.
        
        
           
        
        
          A number of factors influenced how facilities engineering support
            would be provided. Contingency planning for operations in Vietnam
            had not, in any of the joint service plans, developed a requirement
            for facilities engineering forces. While operations in Vietnam were
            substantially different from those assumed in developing contingency
            plans, the fact remained that plans were not developed to support
            facilities once erected during previous sessions of contingency
            planning. The inability to produce the manpower for a military
            facilities engineer force severely limited other military engineer
            capabilities from the outset. Most of the engineer utilities
            detachments intended for facilities engineering were in Reserve
            status, and the decision not to mobilize the Reserve meant that
            these forces would be unavailable. The strict limitations on
            personnel strength in Vietnam and the desire to keep the ratio of
            support troops as low as possible forced consideration of a
            predominantly civilian work force. However, low ceilings were
            imposed on direct hiring, a complex and slow procedure; this left a
            civilian contract force as the only feasible alternative.
            Consequently, with the buildup the Army called upon Pacific
            Architects and Engineers to expand its organization as the pace of
            facilities construction in-
      
        
        [89]
        
      
    
    
        
          creased. The contractor's response was commendable, although not
            without problems. His strength grew from 274 men located at six
            adviser sites in 1963 to a peak strength of over 24,000 in 1968 at
            more than 120 locations.
        
        
           
        
        
          The piecemeal nature of the buildup made it almost impossible to
            predict future requirements or even the eventual location of
            incoming troop units. The system which evolved was to tailor the
            contractor's organization to meet the needs of each installation as
            it was established and expanded. The PA&E work force was made up
            of a combination of U.S. civilians, Vietnamese, and other
            nationalities. The force mix was about 5 percent American, 15
            percent other country, and 80 percent Vietnamese. The contract with
            PA&E grew to approximately $100 million per year, not including
            government-furnished supplies amounting to approximately $20
            million.
        
        
           
        
        
          While the Army relied heavily on Pacific Architects and Engineers,
            it knew that the contractor could not do all the work. His civilian
            workmen could not enter certain areas of the combat zone and would
            go off the job when curfews and strikes were ordered. There were,
            however, approximately 1,450 engineer troops mobilized and deployed
            in Vietnam as utilities detachments and firefighting and water
            purification teams. (See Chart 5.) Military power plant
            operation and water supply companies ranged in size from four to
            forty men. While some of these units operated at the same locations
            as the contractor's forces, they were stationed primarily in
            outlying areas where for security reasons civilians were barred.
        
        
           
        
        
          In addition to the PA&E work force and the engineer utility
            detachments, there were a number of smaller contracts let for
            specific kinds of facilities engineering support. But, except for
            contracts with the Navy and Philco-Ford in I Corps and with Vinnell
            for electric power generation, these contracts will not be discussed
            individually.
        
        
           
        
        
          In sharp contrast to the Army, the Air Force facilities
            engineering forces were predominantly military. During peacetime,
            the Air Force had maintained a significant number of military
            personnel as facility maintenance engineers in its stateside
            installations. This gave the Air Force a good base upon which to
            draw when the conflict in Vietnam developed. A base civil engineer
            force is an integral part of an Air Force wing, and when wings were
            deployed to Vietnam, their base maintenance forces went with them.
            These forces were augmented by Red Horse squadrons (heavy
            maintenance and repair units numbering about 400 men) and Prime BEEF
            teams (small detachments sent for six-month tours to augment the
            base civil engineer forces for specific projects). The Air Force
            made con-
        
        
    
      
        
        [90]
        
      
    
    
        
          siderable use of contracts, but these were usually for special
            tasks, such as power generation and refuse collection.
        
        
           
        
        
          The Navy also experienced a shortage of trained military
            personnel, although it was somewhat better off than the Army in this
            regard. In I Corps, Seebees were assigned to the Public Works
            Department, Naval Support Activity, at Da Nang. The Seabees managed
            the work force augmented by hired foreign nationals and by local
            nationals provided under a service contract with Philco-Ford. The
            work force was made up of about one-third Seabees, one-third foreign
            nationals, and one-third Vietnamese. In contrast to the Army's
            contract with Pacific Architects and Engineers, the Philco-Ford
            contract served primarily to provide skilled local labor. Except at
            a few industrial facilities, the contractor was not responsible for
            over-all management. In addition to the forces assigned to the
            Public Works Department in Da Nang, the Navy activated two
            construction battalion maintenance units and sent them to Vietnam.
        
        
           
        
        
          As previously noted, Pacific Architects and Engineers had to
            organize and staff its forces along the lines of standard Army
            organizations. To control this force, PA&E established a
            Contract Management Office in Saigon and three district offices at
            Saigon, Qui Nhon, and Cam Rahn Bay from which PA&E forces and
            operations at each Army installation were controlled. A highly
            effective communications net was operated independently of the
            unreliable Vietnamese telephone system and of the military
            communications system, which was needed for high-priority
            operational traffic.
        
        
           
        
    
    
      
        
          SEABEES responsible for bridge construction in I Corps
        
        
      
    
    
      
        
          [91]
        
        
      
    
    
        
          Administration of contracts and the technical direction and
            control of the contractor's activities were, until mid-1968, the
            responsibility of the 1st Logistical Command. Within the 1st
            Logistical Command, responsibility for contract management was
            vested in the U.S. Army Procurement Agency, Vietnam (USAPAV). The
            rapid growth of contract work between 1965 and 1967 made it evident
            that better control than the procurement agency and the 1st
            Logistical Command engineering staffs could provide was needed.
            Therefore, the Contract Operations Branch, located at PA&E's
            Contract Management Office in Saigon, was established as a part of
            the Office of the Engineer, 1st Logistical Command. In addition, the
            staff engineers of the Saigon, Qui Nhon, and Cam Ranh Bay Support
            Commands, subordinate commands of the 1st Logistical Command, and
            the staff engineers of the installations within the support command
            areas were delegated appropriate contracting officer's
            representative authority. The Contract Operations Branch consisted
            of an operations branch, a technical inspection branch, and a
            performance and analysis branch. It had the mission of directing the
            contractor's activities and analyzing contract operations and
            expenditures. This new organization facilitated the identification
            and resolution of many problems which resulted in increased
            efficiency and responsiveness in the contractor's work.
        
        
           
        
        
          Increasing construction, real estate, and facilities engineering
            costs resulted in a decision to integrate all Army engineer
            activities in the U.S. Army Engineer Construction Agency, Vietnam (USAECAV),
            in 1968. In July 1968, USAECAV also assumed the facilities
            engineering responsibilities formerly assigned to the 1st Logistical
            Command except for a direct-hire force supporting the Saigon area
            under the direction of the U.S. Army Headquarters Area Command. This
            activity was also later transferred to USAECAV in 1969.
        
        
           
        
        
          Under the Construction Agency organization, district engineer
            offices were established at Saigon, Cam Ranh Bay, and Qui Nhon. The
            district engineers, in turn, supervised the installation engineers.
            This provided a vertical command channel from USAECAV through the
            district engineers to the installation engineers independent of
            other command relationships. This vertical channel, together with a
            substantial increase in the number of military personnel directly
            concerned with supervision of the contractor's operations (212 under
            the Construction Agency as compared to 73 under the 1st Logistical
            Command), substantially improved operations management.
        
        
           
        
        
          Under the new setup, 1st Logistical Command's procurement agency
            retained contracting officer authority, and the contracting
            officers, who exercised technical supervision over the contractor,
        
        
    
      
        
        
          [92]
        
      
    
    
        
          reported to two separate headquarters. To overcome the inherent
            disadvantages in this arrangement, it was proposed to provide the
            Commanding General, USAECAV, with contracting officer authority for
            the facilities engineering contract. This, however, was disapproved
            by the Department of the Army in order to avoid fragmenting
            procurement authority in Vietnam. While this decision did not result
            in the optimum organizational relationships from the viewpoint of
            managing the facilities engineering effort, relations between the
            procurement agency and the construction agency under a memorandum of
            understanding were excellent. Through mutual effort, the
            difficulties inherent in the organizational relationship were
            minimized.
        
        
           
        
        
          The form of the contract with PA&E underwent several changes.
            Originally negotiated as a cost plus a fixed fee in 1963, the
            contract remained in effect until 1970. To increase the contractor's
            incentive in performance of the contract, the Procurement Agency
            assisted by the Construction Agency negotiated a cost-plus-award-fee
            contract in 1969. Under this contract the company was evaluated on
            its performance, and the fee depended upon this evaluation. The new
            agreement appears to have resulted in increased effectiveness and
            efficiency.
        
        
           
        
        
          An effort was made to introduce competition by splitting off the
            Qui Nhon area in 1968 and advertising for new bids. Because PA&E
            was already working in Vietnam and was familiar with facilities
            engineering operations there, the firm had a distinct advantage over
            any competitors. Consequently, the new contract also went to Pacific
            Architects and Engineers. The attempt to introduce competition not
            only proved unsuccessful, but the new contract meant PA&E would
            operate under two distinct contracts. Any thoughts of a second try
            at competition were quietly laid aside, and-the following year the
            Army returned to a single contract.
        
        
           
        
        
          In 1967 PA&E's activities were extended into I Corps following
            deployment of substantial numbers of Army units into the area, which
            had been primarily a Marine Corps and Navy zone of operations.
            Although the Navy was providing logistical support for I Corps, it
            was not in a position to support all Army installations.
        
        
           
        
        
          In 1970, following major shifts in U.S. operations, logistical
            responsibility for I Corps was transferred from the Navy to the
            Army. Consideration was given to extending the PA&E contract to
            cover all of the area, but the decision was made to negotiate a
            contract with Philco-Ford to continue in the areas where they had
            been working under contract to the Navy. This arrangement
            facilitated continuity of operations but had the disadvantage of
            resulting in two different contracts and contractors to supervise.
        
        
    
      
        
        
          [93]
        
        
      
    
    
        
        
          Experience in Vietnam highlighted many administrative, regulatory,
            and other constraints, which indicated areas where improvement was
            required. Vietnam was the first conflict in which peacetime Army
            budget regulations had been stringently applied in a combat zone.
            Many of the peacetime regulations applicable to facilities
            engineering were necessarily prohibitive in nature and cumbersome in
            application. Designed to minimize the diversion of utilities
            engineering resources and to avoid certain statutory violations, the
            application of these regulations in a combat zone greatly inhibited
            the effectiveness of facilities engineering support by both the
            contractor and the utilities detachments. Further examination of
            these regulations as well as the Department of Defense directives
            and the laws on which they were based is required to achieve greater
            flexibility and responsiveness under future combat conditions.
        
        
           
        
        
          The contractor, PA&E, frequently drew criticism for
            overstaffing. Much of his staffing requirements, however, resulted
            directly from the requirement that he organize, staff, and manage
            his efforts strictly in accordance with Army regulations. (Chart
            6)
            This resulted in much of the contractor's effort going into work
            management and production control. While the principles of work
            management are an inherent part of effective operations under any
            conditions, the amount of effort expended in the preparation of
            detailed schedules and work plans was of questionable value under
            the turbulent conditions which prevailed. There was a distinct
            advantage in having the contractor follow Army regulations in
            organizing and managing his force in that this facilitated the
            control and monitoring by the contract officers, but here too
            consideration should be given to adopting simplified procedures for
            combat conditions.
        
        
           
        
        
          A major problem that persisted throughout the conflict, largely
            because of the rapid turnover of military personnel, was the general
            lack of facilities engineering experience. The one-year tour of duty
            was necessary from a morale standpoint, but it had an adverse effect
            on the operations of the engineer detachments and on contractor
            supervision. Most officers assigned to facilities engineering duty
            in Vietnam lacked former experience, and it normally took much of
            their one-year tour to become knowledgeable in facilities
            engineering regulations and requirements. The Vietnam experience has
            highlighted the need for a broader base of both officers and
            enlisted men with facilities engineering training and experience.
        
        
           
        
        
          Perhaps the greatest difficulty in the contractor's operations
            stemmed from the problems he had in obtaining the necessary
            government-furnished supplies and equipment-problems which were not
            resolved until late in the conflict.
        
        
    
      
        
        
          [94]
        
      
    
    
    
    
    
      
        
          [95]
        
        
      
    
    
        
          Despite these difficulties, the facilities engineering support of
            combat forces in Vietnam was an undertaking successfully carried out
            on a scale never before seen in a combat zone. The rest of this
            chapter will discuss a few of the special problem areas.
        
        
           
        
        
          While primarily contracted for facility operation, maintenance,
            and repair, PA&E was used extensively to accomplish construction
            of minor facilities during the major period of the troop buildup
            from mid-1965 to mid-1968. Before the buildup, the small PA&E
            force was primarily engaged in maintenance and repair of leased
            facilities. As more and more troop units arrived in Vietnam, the
            most urgent requirements were to construct defenses followed by
            troop and support facilities. Urgent requirements existed for
            cantonments, airfields, depots, repair shops, and the utilities
            systems needed to service them. Because of its construction
            capability, Pacific Architects and Engineers was called upon to
            provide help in small operations and maintenance funded (under
            $25,000) projects. Paradoxically, although much of its effort went
            into construction, the terms of the PA&E contract did not permit
            the contractor's employment on new construction funded work. This
            meant that he could not construct many of the facilities needed for
            his own use, which would have increased his over-all effectiveness.
            By the end of 1967 the increased capabilities of the construction
            contractors and construction troops made it possible for Pacific
            Architects and Engineers to concentrate on facilities engineering.
            The sharply increased demand for facilities engineering made
            redirection of PA&E effort imperative as more new facilities
            went into use and more troops arrived in the theater. While during
            1965 and 1966 the contractor expended as much as 80 percent of his
            effort on new construction, this figure dropped to 25 percent by the
            middle of 1968 and to below 15 percent in subsequent years.
        
        
           
        
        
          The varying standards of construction and the absence of a
            standard for maintenance and repair proved troublesome throughout
            the conflict. Although the Military Assistance Command in Vietnam
            published over-all standards, wide variations existed. Standards
            ranged from tent frames and Southeast Asia huts to elaborate
            air-conditioned, pre-engineered facilities with high-voltage
            electric distribution systems and modern water and sewage systems.
            The extent of facilities engineering support received by individual
            installations depended on what local commanders needed and on what
            facilities they succeeded in getting built. Until very late in the
            conflict, there were no countrywide standards for planning
            facilities engineering support. As a result, resources were often
            not equitably distributed.
        
         
        
        Fire protection was certainly adequate at Army installations
        
    
      
      [96]
      
    
    
    
        
          
          VIETNAMESE FIREFIGHTER ignores risk to fighting petroleum fire
            at Long Binh.
          
          
          
        
        
           
        
        
          throughout Vietnam. Fire companies were manned primarily by
            PA&E, although there were some military firefighting
            detachments. On a visit in 1969, representatives of the Office of
            the Chief of Engineers pointed out that there were far too many fire
            companies and fire trucks in the theater. Further analysis by the
            Army Engineer Construction Agency led to a substantial reduction in
            fire companies and the cancellation of all outstanding requisitions
            for fire trucks. Although fire protection was possibly overstressed,
            fire prevention was given inadequate attention. While temporary
            structures appropriate to a combat zone were constructed with
            combustible materials like plywood and low-density fiberboard, fire
            hazards could have been appreciably reduced by proper building site spacing. Still, the use of combustible interior partitions and other
            interior finishes and nonexpert installation, extension, and
            modification of electrical systems created serious fire hazards. The
            lesson is evident-more emphasis must be given to fire prevention.
        
        
           
        
        
          Control of insects, rodents, and other pests was a particularly
            challenging problem. Vietnam lacks all but the most basic health and
            sanitation safeguards; malaria and the plague are endemic. Vigorous
            efforts by facilities engineering entomology teams and the rigid
            enforcement of health and sanitation rules turned military bases
            into "islands of health in a sea of disease and
            pestilence." The return of retrograde cargo from Vietnam raised
            the danger of Asiatic insects and rodents being brought back.
            Careful and thorough cleaning of this cargo and treatment with rat
            poison and insecticide dust-as much as 112 tons per
            month-effectively eliminated this danger. Losses of foodstuffs in
            storage from insect infesta-
        
        
    
      
        
        
          [97]
        
      
    
    
        
          tion amounted to millions of dollars annually. During 1970, new
            control techniques for treatment of stored foodstuffs in CONUS
            before shipment and in Vietnam after receipt were adopted.
            Fumigation of railway cars in transit from the mills began in
            September 1970. Experience in the United States to date indicates
            that these procedures will reduce losses of stored foods by as much
            as 98 percent.
        
        
           
        
        
          Chief among the lessons learned from Vietnam was that the
            requirements for facilities engineering support in future conflicts
            must be anticipated during contingency planning, inasmuch as these
            requirements represent a substantial portion of the resources
            required to support such an operation-the total force dedicated to
            facilities engineering (over 25,000) approached the combined
            strength of the two engineer brigades deployed to Vietnam (about
            30,000). The feasibility and, under similar circumstances, the
            desirability of providing the major portion of this force by
            contract was demonstrated in Vietnam. Our experience also clearly
            demonstrated the need for the Army to maintain, in its active force
            structure, an adequate number of military personnel trained in
            facilities engineering to provide management and supervision of
            contractor and direct-hire civilian maintenance forces and to man
            sufficient numbers of military facilities engineering detachments to
            ensure continuity of essential operations in emergency situations.
        
      
        
        
      [98]
        
      
    
    
    
      
       page created 15 December 2001
      
    
    
    
Previous Chapter    
Next Chapter
Return to the Table of Contents